An open letter to Network Rail CEO Andrew Haines

In April 2019 Biggleswade station was awarded ‘Access for All’ funding to provide lifts at the station. Five years on the much delayed scheme has been delayed yet again, and ironically we were informed of this delay in the same week that Andrew Haines set out how Network Rail, the organisation he has been the Chief Executive Officer since 2018, is failing disabled people. Below is my open letter to him sent on 3rd May 2024.


Dear Mr Haines

I am writing to you regarding your appearance at the Public Accounts Committee on 29th April and the step-free access scheme at Biggleswade station.

During your evidence to the committee, you set out Network Rail’s failure to deliver for passengers who require assistance, and gave four main reasons for this:

  1. Incorrect selection of the stations chosen for accessibility improvements.
  2. A lack of understanding of the scope of the schemes selected.
  3. Getting too involved with stakeholders, resulting in an increase in costs.
  4. A lack of competence in managing ‘smaller schemes’ (referring to accessibility improvements).

In the same week that you set out Network Rail’s profound failures, it was a bitter irony to hear that work on the much delayed step-free project at Biggleswade had been halted, with no current estimate of a resumption of the works. Further, this news was relayed to us by the lead of the sixth Network Rail team on the Biggleswade project. Constantly having to deal with different teams makes progress and cooperation far more difficult. Does Network Rail have a staff retention problem?

The constant chopping and changing of your project teams has resulted in poor communication between Network Rail and the various stakeholders involved. The latest example of poor communication is the belated announcement of the latest ‘delivery challenges’, which must have been known about for some time.

We understand that projects will frequently face delays for one reason or another. However, in the case of Biggleswade, there have been some inexplicable delays for which we have not been provided with credible answers. These include an 18-month delay, which Network Rail implied was the result of a four-month delay while we insisted on the original specification being included in the project. Perhaps this is an example of the ‘excessive stakeholder involvement’ you discussed at the committee?

Our bid for ‘Access for All’ funding for Biggleswade was submitted around the time you became CEO of Network Rail in 2018. Yet, almost six years on, the station remains inaccessible to many, with now no firm date for lifts at the station

While I respect your openness around these fundamental failures (set out in your four points above) to address the issues that have such a detrimental impact on people disabled by the railway, after six years of failure in this area under your tenure, some may have considered their position. Do you believe you have the qualities to turn this around? If you do believe you have the necessary skills, knowledge and experience, why have these not been brought to bear to deal effectively with the profound failures you set out in your evidence to the committee?

I look forward to your reply on the issues raised in this email and would be grateful if you would keep a close eye on the Biggleswade project, and impress upon your team the importance of open and timely communication.

Due to the high level of public interest in this issue, please regard this email and any reply as an open letter.

Yours sincerely

Julian Vaughan

Chair Bedfordshire Rail Access Network

3rd May 2024