UK railways ‘Access for All’ audit


This is a blog covering the status of the UK railway stations provided with ‘Access for All’ (AfA) funding to provide step-free access. The ‘Access for All’ funding programme aims to provide an accessible route onto and between railway station platforms and was launched in 2006.

Since its launch, step-free routes have been provided at approximately 200 stations. It is often quoted that more than 75% of rail journeys are now through stations with step-free access. I view this as misleading as by definition this figure includes non-disabled people and makes no reference to the thousands of railway platforms across the UK that remain ‘no-go’ areas for disabled people.

The information below is divided into three sections.

  1. Stations awarded AfA funding in 2014 for Control Period 5 (2014-2019).
  2. The 27 stations awarded AfA funding in 2014, but deferred as a result of the ‘Hendy Report’ to Control Period 6.
  3. Stations awarded AfA funding in 2019 for Control Period 6 (2019-2024)

The results make for grim reading, and some stations will be waiting for well over a decade after their original funding was agreed. Read more about these stations here: https://julianvaughan.blog/2024/08/09/a-decade-of-step-free-delay/

This process has been made significantly more difficult due to Network Rail’s inability to give out anything other than ‘good news’. This insidious and pervasive corporate culture is endemic across the UK and reduces both transparency and accountability.

Any errors are mine alone and I do regard the below as a ‘live’ document. Please feel free to get in touch with any corrections.

You are welcome to email me at: ukrailaccessnetwork@gmail.com

I have linked to sources where available and I provide further resources and further reading at the bottom of this post. Completed projects are highlighted in green.

Regarding the stations awarded funding in 2019 for Control Period 6. I understand that following a ‘deep dive’ review into ‘AfA’ projects by the Department for Transport, the deadline for unfinished stations has been extended from 2024 to March 2026.

There is much discussion about the affordability of providing an accessible rail network. I discuss this in this blog: https://julianvaughan.blog/2024/07/16/can-we-afford-not-to-have-an-accessible-railway/

On to the data, starting with the stations awarded funding in 2014.

*Please note that these tables were created in September 2024 and updated in January 2025 and August 2025.


How are stations awarded ‘Access for All’ funding in 2014 progressing?

StationCompletion Status and Comments
TeddingtonWorks due to start September 2023 and finish Spring 2024. https://teddingtontown.co.uk/2023/09/13/work-finally-starts-on-teddington-station-lifts/

https://www.networkrailmediacentre.co.uk/news/accessibility-improvements-afoot-at-barnes-and-teddington-stations

*Update 15.01.25* The station is only partially accessible with no cross-platform step-free access.
Cost £4.2m
*Update 04.08.25* The station is now step-free. Press release from Network Rail on 23rd May 2025 announcing opening – cost revised up to £5.4m.
https://www.networkrailmediacentre.co.uk/news/teddington-becomes-latest-station-in-south-west-london-to-receive-accessibility-improvements#
Category B2 station.
Managed by: South Western Railway
CrawleyComplete.
Palmers GreenDue for completion mid 2024 https://www.london.gov.uk/who-we-are/what-london-assembly-does/assembly-member-press-releases/palmers-green-and-alexandra-palace-station-upgrades-make-progress
*Update* Construction now due to start in 2025 https://enfielddispatch.co.uk/network-rail-sorry-for-delays-to-station-accessibility-upgrade/
Managed by: Great Northern

*Update 18th August 2025* Direct from Network Rail Senior Public Affairs Manager: “In 2019, the Department for Transport announced a feasibility study to explore the possibility of making Palmers Green railway station step-free. (Author’s note: Palmers Green was actually granted funding in 2014 at the start of Control Period 5) Feasibility studies, as you know, investigate the potential affordability and deliverability of a project, as well as the potential benefits in meeting the objectives of the Access for All programme, passenger demand forecasts, and economic and transport benefits. Once completed, the feasibility study is submitted to the Department for Transport to determine the next steps for the project.
The proposed Access for All Scheme at Palmers Green railway station is particularly complex due to space constraints around the platforms. These challenges mean that the scheme is remains in the design stage, with cost and benefit estimates currently under review. We expect to have more details available in the coming months and will keep you updated on the project’s status”.
Coulsdon SouthComplete.
ShortlandsDue for completion in Spring 2025.
https://www.networkrail.co.uk/running-the-railway/our-routes/kent/shortlands-station-access-for-all-improvements/
Cost £8.5m
*Update* Lifts opened 28th April 2025.
https://newsroom.southeasternrailway.co.uk/news/shortlands-station-accessibility-scheme-completed
Managed by: Southeastern
PlumsteadComplete March 2024 – National Rail Enquiries Map is out of date. The National Rail Enquiries map is still out of date as of 4th August 2025 as it does not show the lifts – Southeastern notified of error.
Cost £4.6m
Managed by: Southeastern
SelhurstComplete.
CarshaltonComplete August 2019.
Canterbury EastComplete.
BexleyLifts are open, although the National Rail Enquiries Map shows no lifts at the station – Southeastern notified of the error.
Managed by: Southeastern
Ewell WestComplete.
Alexandra PalaceDue for completion by Spring 2025. https://www.london.gov.uk/who-we-are/what-london-assembly-does/assembly-member-press-releases/palmers-green-and-alexandra-palace-station-upgrades-make-progress
Cost £8.1m
*Update* Still not step-free as of 04.08.25.
Managed by Great Northern

*Update 18th August 2025* Direct from Network Rail Senior Public Affairs Manager: “Regarding accessibility improvements at Alexandra Palace railway station as part of the Government’s Access for All scheme, I can confirm that these plans are also in the design stage, with a new contractor on board who is finalising the design and preparing a construction schedule”.
TringComplete in 2020 – cost £5.8m.
StetchfordComplete, but incorrect information on the National Rail Map.
Notified in October 24 and January 25. *Update* The lift information has now been corrected – checked August 2025.
Managed by West Midlands Railway
MeolsComplete 2020.
Mills HillComplete 2020.
Torquay‘In Development’ https://www.networkrail.co.uk/communities/passengers/access-for-all-improving-accessibility-at-railway-stations-nationwide/
TotnesComplete.
ScunthorpeComplete although lifts only open during staffed hours – therefore should be classed as a B2 station rather than a Category A station. There are 5 W/B trains towards Doncaster after 20.00 when the station staffing is withdrawn.
HeadingleyCompleted in May 2019, although the National Rail Enquiries map still does not show the lifts at the station. *Update August 2025 – the NRE map still doesn’t show the lifts – Northern and NRE have both been reminded. https://www.nationalrail.co.uk/stations/headingley/
Taffs WellLifts due to be completed imminently.
https://tfw.wales/sites/default/files/2023-04/Taff%27s%20Well%20AFA%20April%20-%20ENG.pdf
August 2025 – still at Category B2 station
https://www.nationalrail.co.uk/stations/taffs-well/
TreherbertComplete – Accessible ramp to platform.

How are stations awarded ‘Access for All’ funding in 2014, but then deferred to Control Period 6 (2019-2024) progressing?

StationTRAIN OPERATING COMPANY Completion Date Comments
ALFRETONEast Midlands RailwayAt March 2023 – Due Spring/Summer 2024
https://www.networkrailmediacentre.co.uk/news/work-starts-on-accessibility-upgrade-project-at-alfreton-station
*Feb 2025 Update – due for completion early 2025
*August 2025 Update* Lifts were opened on 3rd June.
https://www.networkrailmediacentre.co.uk/news/derbyshire-stations-accessibility-scheme-is-completed
Out of date information (no mention of the lifts) on either the NRE of ‘Fab Map’ websites as af 5th August.
Cost £6.75m
TOC emailed for comment, no reply
BARNESSouth Western RailwayDue early 2024, delayed to end of 2024.
https://www.networkrailmediacentre.co.uk/news/accessibility-improvements-afoot-at-barnes-and-teddington-stations

https://www.networkrail.co.uk/running-the-railway/our-routes/wessex/wessex-access-for-all-schemes/

*Update August 2025* Lifts opened February 2025 https://www.networkrailmediacentre.co.uk/news/barnes-station-takes-railway-accessibility-forward-in-south-west-london
Cost £5.7 million

*Update August 2025* Cost £8.3m (source Network Rail press release.
BARRY (TOWN)Transport for WalesOpened July 2022
BATTERSEA PARKSouthernNetwork Rail 2006 Press Release: https://www.networkrailmediacentre.co.uk/news/battersea-park-station-on-track-for-major-makeover

No firm date for completion – estimate end of 2026.
https://www.ianvisits.co.uk/articles/battersea-park-station-upgrade-plans-could-provide-step-free-access-65819/
As of Sep 23, cost estimate £20 million – £4m from AfA, the rest from developers’ contributions.
CATHAYSTransport for WalesLifts currently being built, estimated completion early 2025

*Update August 2025* Lifts not in service TfW contacted for update.

*Update 9th September 2025* FOI response from TfW: “Progress: Design & Build Contractor appointed. Detailed design being worked through (TfW Plan of
Work Stage E). Estimated completion of the project: Spring 2027″
CHATHAMSoutheasternOpened September 2022Cost £5.8 million
GARFORTHNorthernLifts due to open August 2024.
https://www.networkrailmediacentre.co.uk/news/first-of-its-kind-passenger-footbridge-opens-at-west-yorkshire-station
*29th July Update from NR – lifts due to open in the Autumn 2024.
*Update 5th August 2025* Northern confirm via Twitter that the lifts have not yet opened – although data on the NRE website suggests they are open!
*Update 8th August 2025* Network Rail states via email that the works at Garforth station are complete.
*Update 11th August 2025* NRE website states lifts are out of order.
Cost £6 million

‘Beacon’ Bridge – no further news re completion.
GRAYSc2cWork due to start Jan 2024 and take 12 months.
https://www.networkrailmediacentre.co.uk/news/grays-station-accessibility-improvements-to-begin-in-september
*June 2025 Update* lifts due to open by July – as per local MP Facebook post.
*5th August update* Lifts not open.
No ORR station categorisation.
HITHER GREENSoutheasternNo information on completion.
*Update* Summer 2025 – work starting March 2025 – due to complete Autumn 2027. https://www.networkrail.co.uk/running-the-railway/our-routes/kent/kent-and-south-east-london-railway-upgrade-plan/hither-green-station-access-for-all-improvements/
3.3m passengers annually.
LIVERPOOL CENTRALMerseyrailLifts opened
LLANELLITransport for WalesLifts currently being built
*Update August 2025* Lifts are now open.
LUTONThameslinkAs of Sep 2023, work due to start Spring 2024.
*Update – work due to start August 2024
https://www.networkrailmediacentre.co.uk/news/construction-work-begins-on-major-improvements-at-luton-station
*Further update – work due to start Spring 2025.
https://www.lutontoday.co.uk/news/transport/an-accessible-station-has-never-been-more-necessary-work-on-lifts-and-footbridge-at-luton-railway-station-delayed-until-spring-2025-4806679
*Update* Estimated completion now 2026
MARKET HARBOROUGHEast Midlands RailwayLifts opened 2020?
https://www.railengineer.co.uk/affordable-by-design-market-harborough-station-revisited/
NORTHALLERTONTrans Pennine ExpressOpened March 2022
PECKHAM RYESouthernWork due to start 2026

*July 2025 Update* Work paused ‘until further notice’.
https://southwarknews.co.uk/area/peckham/peckham-rye-station-upgrade-postponed-in-recent-spending-review/
https://www.networkrail.co.uk/running-the-railway/our-routes/kent/kent-and-south-east-london-railway-upgrade-plan/peckham-rye-station-redevelopment/
PETTS WOODSoutheasternLifts opened early 2024Cost £10.79m
QUEEN’S PARKLondon UndergroundDelayed – No clear data available
SEVEN SISTERSLondon OvergroundNo data available
*Update January 2025* Delayed due to funding shortfall. https://haringeycommunitypress.co.uk/2025/01/17/plan-to-install-lifts-at-seven-sisters-station-put-on-hold-amid-funding-issues/
SOUTHEND EASTc2cNo data available
*Update June 2025 – estimated completion end of 2026. https://www.networkrailmediacentre.co.uk/news/contract-awarded-for-accessibility-improvements-at-second-southend-station

https://www.networkrailmediacentre.co.uk/news/reminder-invitation-to-the-chalkwell-and-southend-east-station-community-events
ST MARY CRAYSoutheasternLifts opened February 2022
STREATHAMSouthernLifts opened December 2023
THEALEGreat Western RailwayWork due to be completed either Winter 23/24 or Spring 2024 depending on source.
https://www.networkrailmediacentre.co.uk/news/one-step-closer-major-milestone-reached-in-improving-accessibility-at-theale-station
*Further update – lifts delayed to November 2024. As of January 2025 lifts are still not in service.
https://www.newcivilengineer.com/latest/network-rail-criticised-for-late-opening-of-theale-station-access-for-all-footbridge-11-12-2024/
*Final Update – Lifts opened at this station on 16th January 2025.
https://thealestationusers.wordpress.com/2025/01/16/update-from-us-thursday-16th-january-2025-its-over/

Cost £9.5m
TREFFORESTTransport for WalesNo data availableCurrently classed as B2 station as per ORR classification.
WALTON-on-THAMESSouth Western RailwayLifts Open August 2024.
https://www.networkrail.co.uk/running-the-railway/our-routes/wessex/wessex-access-for-all-schemes/#wandsworth
Classed as B2 station due to steep gradient of ramp to platform 1.
WARWICKChilternWork currently paused
*Friday 6 September 2024 – work restarted estimated 6 months.
*Update June 2025* Subway re-opened and lift shaft being put in place. https://www.networkrailmediacentre.co.uk/news/warwick-station-subway-reopens-to-passengers
*Update 6th August 2025* Lifts not yet in operation.
Work paused due to finding foundations of original station.
WESTON-SUPER-MAREGreat Western Railway*Update July 2024*
https://www.thewestonmercury.co.uk/news/24457906.network-rails-plans-install-two-lifts-weston-railway-station/
*Update 21st August 2025* from Network Rail Community Relations: “Within the Western region, we have St Erth, which is expected to be complete in November this year, and Weston-Super-Mare, which is expected to be completed in January 2027”.
WORCESTER SHRUB HILLWest Midlands RailwayWork is due to be completed by the end of 2023. No lifts working at present.
https://www.worcesternews.co.uk/news/20989317.lift-installed-shrub-hill-station-2023/

https://www.networkrailmediacentre.co.uk/news/station-platform-canopies-to-be-restored-at-worcester-shrub-hill
Currently classified as a B3 station

Update direct from Network Rail received on 13th August 2025: In response to your information request as regard Worcester Shrub Hill.
Funding for a lift scheme for Worcester Shrub Hill station has been committed to as part of the government’s access for all scheme. This scheme is currently in design phase and therefore we’re unable to share any estimated completion dates. Members of the public will be kept informed of next steps once a timeline has been agreed.

How are stations awarded ‘Access for All’ funding in 2019 (Control Period 6) progressing?

STATIONTrain Operating CompanyProgressComments
ABERGAVENNYTransport for WalesDue to complete Early 2025
*Update May 2025* Lifts and beacon Bridge opened. https://www.abergavennychronicle.com/news/step-free-access-available-for-passengers-in-abergavenny-793425
NR press release.
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Abergavenny
ANNIESLANDScotRailDue to complete Sep 2024email from ScotRail.
*Update* now open October 2024.
https://www.networkrailmediacentre.co.uk/news/anniesland-station-now-step-free-as-unique-accessibility-project-is-completed
BEACONSFIELDChilternNo Data found
*update 6th August 2025* No information available on progress – Network Rail contacted.

*Update 7th August 2025* Response from Chiltern via Twitter – they’re awaiting a response from Network Rail pending a ministerial budget review.
BEESTONEast Midlands RailwayDue to complete Autumn 2024
*Update August 2025* Apparently the lifts are now open, although the National Rail Access Map still states there are no lifts at the station.
Added March 2020 Budget
https://www.networkrailmediacentre.co.uk/news/engineers-begin-work-on-improving-accessibility-at-beeston-station
BIGGLESWADEGreat NorthernOriginally due to be complete in late 2022. Now no completion date.
*Update* Now due for completion December 2025.
https://www.networkrailmediacentre.co.uk/news/accessibility-upgrades-to-restart-at-biggleswade-station-this-january
*Update August 2025* Lifts still on course to be opened December 2025.
BIRKENHEAD PARKWorks complete
BRIDLINGTONWorks complete
BROAD GREENNorthernClosed for refurb until Winter 2024.

*Update Jan 2025* Lifts due for completion by December 2026 – reason for delay – change of contractor. https://www.liverpoolecho.co.uk/news/liverpool-news/metro-mayor-puts-northern-on-30860194
CAERPHILLYTransport for WalesNo Data found

*Update August 2025* still no data found on progress.

*Update 9th September 2025* FOI Request response from TfW: “Step free access at Caerphilly is in development as part of the Caerphilly Interchange proposal.
Estimated completion dates are yet to be confirmed and subject to funding approvals.
The scheme forms part of the Southeast Wales Corporate Joint Committee’s Regional Transport Plan
and Regional Transport Development Plan, full details of which are available on Cardiff Capital
Region’s website”.
CATFORDWorks complete
CHALKWELLc2cDelayed to 2026
*August 2025 Update* Expected to have lifts open by end of 2026.
https://www.networkrailmediacentre.co.uk/news/reminder-invitation-to-the-chalkwell-and-southend-east-station-community-events
https://www.echo-news.co.uk/news/24201659.chalkwell-station-accessible-lift-delay-extends-2026/
CHORLEYNorthernDue to be completed in August 2024 – no update found in Jan 2025.
*Update April 2025*
https://www.parallelparliament.co.uk/question/41974/chorley-station-access
*Update 7th August 2025* ‘Repairs’ still being carried out – source Northern Twitter reply.

*Update 8th August* via email from Network Rail – “We are currently reviewing all of the previous design work in parallel with engaging with our supply chain for continued design and onward delivery.
We’re too early in the handover stage to be able to accurately communicate either a timescale but, rest assured, Network Rail are absolutely committed to delivering the scheme. We have a dedicated Access for All delivery organisation who will be undertaking the work.
Once we have a timescales these will be set out in upcoming press releases”.
CRICKLEWOODThameslinkIn development – delayed in March 2024.
*Update 11th August 2025*
Direct from Network Rail – Community Relations Manager East Midlands Route. “The proposed Access for All scheme at Cricklewood station is particularly complex due to the limited access for railway closures, signalling infrastructure interventions required and delivery that would struggle to keep the station fully operational due to platform widths. These challenges mean the scheme remains in the design stage with cost and benefits estimates under review”.
*Author’s personal view. The mention of a cost/benefit analysis review, along with the layout issues, puts completion of this project in doubt in a reasonable timescale.
CROWBOROUGHWorks complete £4.7m
CROYWorks complete
CWMBRANTransport for WalesDue to be completde by late Summer/ end of Autumn 2024 depending on which press release you read.

*Update March 2025* Lifts opened on 17th March.
https://www.networkrailmediacentre.co.uk/news/cwmbran-stations-new-lifts-and-footbridge-are-officially-opened-making-travel-easier-than-ever-for-passengers
Passenger Numbers 385,000
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Cwmbran

https://www.networkrailmediacentre.co.uk/news/mp-for-torfaen-sees-progress-on-accessible-footbridge-at-cwmbran-station-as-significant-milestone-is-reached
DAISY HILLNorthernDue to complete Dec 2024/April 2025
*Update April 2025*
Lifts opened on 22nd April.
https://news.tfgm.com/press-releases/9fbaa73e-25f5-4095-b682-108d9ff0ea1c/daisy-hill-station-now-step-free-transforming-access-for-passengers
Cost: £4m
https://memuknews.com/infrastructure/civil-structural-engineering/work-to-improve-accessibility-at-greater-manchester-stations-to-start-in-spring/

https://www.northernrailway.co.uk/engineering/daisyhill-irlam#
DUMFRIESWorks complete
EAGLESCLIFFENorthernDue to complete Autumn 2025.
https://www.networkrailmediacentre.co.uk/news/92-tonne-bridge-lifted-into-place-at-eaglescliffe-station
Added March 2020 Budget
https://www.networkrailmediacentre.co.uk/news/work-starts-on-multi-million-pound-improvement-scheme-at-eaglescliffe-railway-station
EAST GRINSTEADSouthernWorks Complete Sep 22 £4.5mAdded March 2020 Budget
ERIDGEWorks CompleteAdded March 2020 Budget
FLINTTransport for WalesDue to complete by end of 2024.
*Update August 2025* Lifts have now opened – no info on exact date.
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Flint
*Official Opening 2nd October 2025* Cost £5.5m.
https://www.networkrailmediacentre.co.uk/news/flint-railway-station-now-step-free-in-major-boost-for-accessibility
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Flint
FLITWICKThameslinkNo firm date for completion
*Update 1st October 2024 – delayed until mid 2025 or later*

*Update 11th August 2025* Direct from Network Rail’s East Midlands Route Community Relations Manager. “We completed the initial survey works earlier this year, and we’re finalising the contract with the supplier for the remaining surveys and design works, which are proposed to be completed in Autumn 2025. During this phase, we’ll work with the supplier to confirm the programme for detailed design and delivery”.
Added March 2020 Budget. Originally due to be completed by March 2024.
https://www.bbc.co.uk/news/articles/c72qj230xg3o

*Author’s personal view. My experience is that there is a lead time of approximately 12 months from the completion of the design stage to the opening of lifts. Therefore, I do not expect the station to become step-free until late 2026.
HACKNEY DOWNSLondon OvergroundAs of Aug 2024 work not startedhttps://www.standard.co.uk/news/transport/hackney-downs-step-free-access-upgrade-project-overground-station-accessibility-rail-b1177522.html

https://www.hackneycitizen.co.uk/2024/08/22/step-free-access-delay-hackney-downs-overground-station/
HANDFORTHNorthernDue to be complete early 2026https://www.handforthstation.org.uk/access-for-all-2/
HERNE BAYSoutheasternDue to complete Winter 2024
*Update March 2025* Lifts opened in March 2025.
https://www.networkrail.co.uk/running-the-railway/our-routes/kent/herne-bay-station-access-for-all-improvements/
https://www.networkrail.co.uk/running-the-railway/our-routes/kent/herne-bay-station-access-for-all-improvements/#
HERTFORD NORTHGreat NorthernIn development – due Jan 2025

*Update Jan 2025*
New contractor being sought – potential delay to 2026. https://hertford.org.uk/local-news/1589/station-lift-delayed-further
*Update April 2024* https://x.com/JulieMarsonMP/status/1776268635293536554
HILLSIDEWorks complete
HUNT’S CROSSWorks complete
IRLAMNorthernDue to complete Jan 2025/May 2025. Update May 2025* Lifts opened 14th May. https://www.messengernewspapers.co.uk/news/25159957.two-new-lifts-installed-irlam-railway-station/https://news.tfgm.com/press-releases/a7877f7b-085f-46ea-8678-2859b3bf614a/work-to-improve-accessibility-at-greater-manchester-stations-to-start-in-spring

https://www.northernrailway.co.uk/engineering/daisyhill-irlam#
ISLEWORTHWorks complete
JOHNSTONEWorks complete
KINGS LANGLEYLondon Northwestern Railway3 Lifts ‘in development’ – no data
*Update August 2025* No data found.
LEATHERHEADSouthernDue to complete Spring 2025 £6.2m
*Update April 2025* Lifts opened. https://www.networkrail.co.uk/running-the-railway/our-routes/sussex/leatherhead-station-access-for-all-improvements/
The Rail Delivery Group’s National Rail Access map states that there are no lifts at the station and the NRE map of the station has no lifts indicated.
https://www.networkrailmediacentre.co.uk/news/leatherhead-station-in-south-london-will-soon-benefit-from-two-new-16-person-capacity-lifts-and-a-new-footbridge-which-will-make-the-station-fully-accessible
LUDLOWTransport for WalesDue to be completed Sep 2024.
*Update February 2025* Lifts opened. https://www.networkrailmediacentre.co.uk/news/ludlow-stations-new-lift-opens-and-will-transform-access-for-passengers-1
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Ludlow

https://www.bbc.co.uk/news/uk-england-shropshire-67099887
MENSTONNorthernDue to complete Feb 2025.
*August 2025 Update* No lifts at the station. Could not find further updates.

*8th August 2025 Update* Provided by Network Rail via email: “Work at Menston is due to be completed next year”.
https://www.thetelegraphandargus.co.uk/news/24076952.government-confirms-work-due-start-menston-station/

https://www.shipleyconservatives.org.uk/news/minister-confirms-start-date-menston-station-access-all-scheme
MILL HILL BROADWAYThameslinkNo work started as of March 2024.
*August 2025 Update* No info found.
https://barnetpost.co.uk/2024/03/26/barnet-politicians-slam-government-on-step-free-access/

https://www.theyworkforyou.com/wrans/?id=2024-03-25.20273.h
NEWTOWNTransport for WalesDue to be completed by Autumn 2024/ end of 2024.

*Update* Lifts opened 1st April 2025. https://www.networkrailmediacentre.co.uk/news/new-lifts-open-at-newtown-station
https://www.networkrail.co.uk/running-the-railway/our-routes/wales/improving-station-accessibility-in-wales-and-borders/#Newtown

https://www.networkrailmediacentre.co.uk/news/ms-for-montgomeryshire-sees-progress-on-accessible-footbridge-at-newtown-station
PORT GLASGOWWorks CompleteFinished Dec 2023 https://www.inverclyde.gov.uk/news/2023/dec/official-opening-of-port-glasgow-train-station-s-new-accessible-footbridge-and-lifts
RETFORDWorks complete
SELBYTransPennine ExpressDue to complete June 2023https://www.networkrailmediacentre.co.uk/news/step-free-selby-upgraded-footbridge-and-new-lifts-project-set-to-begin
Awaiting update from Network Rail: email sent 10/09/2024
*Update 19th September – lifts opened on Monday 16th September.
SHOTTONTransport for WalesNo data available. Not step-free as per National Rail Accessibility Map 15.01.2025.
*Update August 2025* No update found.
Awaiting update from Network Rail: email sent 10/09/2024 no update received.
SMETHWICK ROLFE STREETWest Midlands RailwayWork due to be finished July 2022https://www.networkrailmediacentre.co.uk/news/work-to-start-on-new-passenger-lifts-at-smethwick-rolfe-street-station#
Awaiting update from Network Rail: email sent 10/09/2024
*Update 11th September – the station lifts opened in Sep 2022. The data on the Access Map and NRE website map does not show any lifts. I have raised this with WMR.
ST ERTHGreat Western RailwayDue to complete in Spring 2024. As of 15.01.2024 not completed.
*Update Nov 2024* Bridge deck installed. Details below.
https://www.networkrailmediacentre.co.uk/news/important-milestone-reached-as-bridge-deck-and-temporary-staircases-installed-for-new-footbridge-at-st-erth
*Update April 2025* Shuttle taxi service to be provided between the two car parks to help with cross platform access – source NRE station descriptor.

*Update 21st August 2025* from Network Rail Community Relations: “Within the Western region, we have St Erth, which is expected to be complete in November this year, and Weston-Super-Mare, which is expected to be completed in January 2027”.
https://www.networkrailmediacentre.co.uk/news/work-begins-to-bring-step-free-access-to-st-erth
SOUTH CROYDONSouthernNo data
*Update July 2025* Money to be provided for feasibility study as part of £92b funding for rail and road projects.
https://www.thisislocallondon.co.uk/news/25300651.government-backs-plan-lifts-south-croydon-station/
*Note – this station was already provided funding in 2020!
Added March 2020 Budget
https://www.networkrailmediacentre.co.uk/news/four-stations-on-southern-and-thameslink-routes-in-the-south-to-benefit-from-network-rail-delivered-accessibility-improvements
ST MICHAELSWorks complete
STONELEIGHSouth Western RailwayDue to complete Summer 2024.
*Update April 2025* Lifts opened.
https://www.networkrailmediacentre.co.uk/news/accessibility-upgrades-provide-further-improvements-to-stoneleigh-station-in-surrey
Cost: £9.1m
https://www.networkrail.co.uk/running-the-railway/our-routes/wessex/wessex-access-for-all-schemes/#stoneleigh
STOWMARKETGreater AngliaWork due to start September 2023 – Modular design.
*Update August 2025* Lifts due to open end of 2025.
https://www.networkrail.co.uk/running-the-railway/our-routes/anglia/improving-the-railway-in-anglia/anglia-access-for-all-schemes/
Cost: £5.5m
https://railuk.com/railway-stations/greater-anglia-continues-work-on-revolutionary-stowmarket-station-bridge/
https://www.newcivilengineer.com/latest/first-order-in-for-revolutionary-modular-railway-footbridge-01-06-2022/
TENBYTransport for Wales‘In development’ – no further dataAwaiting update from Network Rail: email sent 10/09/2024
TODMORDENNorthernUnder Construction
*Update June 2025* FOI request reply unable to give a completion date – due to a government spending review in June 2025.
https://www.whatdotheyknow.com/request/todmorden_station_lifts/response/3033953/attach/3/FOI202500817%20Response.pdf?cookie_passthrough=1

*Update 8th August 2025* from Network Rail via email:
“We are currently reviewing all of the previous design work in parallel with engaging with our supply chain for continued design and onward delivery.
We’re too early in the handover stage to be able to accurately communicate either a timescale but, rest assured, Network Rail are absolutely committed to delivering the scheme. We have a dedicated Access for All delivery organisation who will be undertaking the work.
Once we have a timescales these will be set out in upcoming press releases”.
TOOTINGThameslinkDue to be completed in Autumn 2024/January 2025
*Update* Lifts opened February 2025.
https://www.networkrail.co.uk/running-the-railway/our-routes/sussex/tooting-station-access-for-all-improvements/
Added March 2020 Budget
https://www.networkrail.co.uk/running-the-railway/our-routes/sussex/tooting-station-access-for-all-improvements/

https://www.networkrailmediacentre.co.uk/news/four-stations-on-southern-and-thameslink-routes-in-the-south-to-benefit-from-network-rail-delivered-accessibility-improvements
UDDINGTONWorks complete
WALKDENNorthern‘In development’ – no further data.
*Update -delayed by a historic mineshaft found when doing prep work. https://www.networkrailmediacentre.co.uk/news/network-rail-investigating-historic-mine-found-beneath-walkden-station-during-accessibility-upgrade
*August 2025* No further update.
Added March 2020 Budget.
https://www.railadvent.co.uk/2024/02/greater-manchester-mine-shafts-found-in-station-work.html
WANDSWORTH TOWNSouth Western Railway‘In development’
*Update August 2025* No further info available.
Due to start on site in late 2024.
https://www.networkrail.co.uk/running-the-railway/our-routes/wessex/wessex-access-for-all-schemes/#wandsworth
WELLINGTONWest Midlands Railway‘In development’ – not started as of May 2024.

*Update August 2025*
Work not due to start until Autumn 2026 “at the earliest”.
https://www.bbc.co.uk/news/articles/cq5gl4n7eleo
https://www.bbc.co.uk/news/articles/czdd5k30w38o

Julian Vaughan

10th September 2024 – and amended on various dates up to 15th January 2025 and August 2025.


Sources and Further Reading:

Control Period 5 AfA Announcement: 29th April 2014 https://hansard.parliament.uk/commons/2014-04-29/debates/14042933000010/AccessForAll(Funding)

Control Period 6 AfA Announcement: 4th April 2019 https://www.gov.uk/government/speeches/access-for-all-73-stations-set-to-benefit-from-additional-funding

Control Period 7 AfA Announcement: 29th May 2024 https://www.gov.uk/government/publications/railway-stations-awarded-access-for-all-accessibility-funding

Starmer, Rail Accessibility and Tanni GT: 1st September 2024 https://julianvaughan.blog/2024/09/01/starmer-rail-accessibility-and-tanni-gt/

Access for All: Nominated stations for Control Period 7 – 310 were nominated, of which 50 were selected: https://julianvaughan.blog/2024/07/17/access-for-all-nominated-stations/

Actions, not words needed on rail accessibility: 30th April 2024 https://julianvaughan.blog/2024/04/30/actions-not-words-needed-on-rail-accessibility/