UK railways ‘Access for All’ audit

This is a blog covering the status of the UK railway stations provided with 'Access for All' (AfA) funding to provide step-free access. The 'Access for All' funding programme aims to provide an accessible route onto and between railway station platforms and was launched in 2006. Since its launch, step-free routes have been provided at … Continue reading UK railways ‘Access for All’ audit

Biggleswade step-free update – 7th Sep 2024

On Wednesday 4th September we had the latest meeting with Network Rail regarding progress (or lack of it) towards a step-free Biggleswade station. The last meeting took place on 24th July and you can read a full update from that meeting here: https://julianvaughan.blog/2024/07/24/access-for-all-biggleswade-july-2024-update/ In brief at the previous meeting we were told that the new … Continue reading Biggleswade step-free update – 7th Sep 2024

Starmer, Rail Accessibility, and Tanni GT

It was great to hear Keir Starmer talk about rail accessibility being a 'basic requirement' following the dreadful experience Tanni Grey-Thompson suffered on an LNER train earlier this week. He was also correct in pointing out that many other people, without Tanni's profile and reach, would have had similar experiences across the UK rail network. … Continue reading Starmer, Rail Accessibility, and Tanni GT

A decade of step-free delay

In 2015, Sir Peter Hendy, now Lord Hendy and currently Minister of State for Rail, was appointed as Chair of Network Rail and tasked to conduct a review of the enhancement programme for Control Period 5, which ran from 2014-2019. From the resulting 'Hendy Report' this programme was "prioritised to reflect the government's commitments to … Continue reading A decade of step-free delay

‘Access for All’ Biggleswade – July 2024 Update

Today, Wednesday 24th July, we met once again with Network Rail and local stakeholders including local Councillors and local MP, Richard Fuller. You can read my previous update from our last meeting in May, which announced a further delay here: https://julianvaughan.blog/2024/05/09/lifts-at-biggleswade-delayed-until-summer-2025/ At the last meeting, we were told that a new quote from the contractor … Continue reading ‘Access for All’ Biggleswade – July 2024 Update

Access for All – nominated stations

On 24th May 2024, the government announced the 50 stations set to benefit from the ยฃ350 million of funding for step-free access as part of the funding settlement for Control Period 7 (2024-2029). You can find the full list here: https://www.gov.uk/government/publications/railway-stations-awarded-access-for-all-accessibility-funding/railway-stations-awarded-access-for-all-accessibility-funding *South Croydon makes an appearance in this list, even though it was actually awarded … Continue reading Access for All – nominated stations

Can we afford not to have an accessible railway?

On 24th May the Department for Transport announced the railway stations set to benefit from the latest round of 'Access for All' (AfA) funding for Control Period 7 which runs from 2024-2029. Having been part of the campaign group, I was delighted to see Leagrave station on the list. However, the ยฃ350 million allocated for … Continue reading Can we afford not to have an accessible railway?

ASLEF union backs UK rail accessibility!

As a campaigner for rail accessibility, a train driver and a proud member of the ASLEF union, I am delighted that yesterday ASLEF adopted the motion which I wrote for debate at ASLEF's Annual Assembly of Delegates (AAD), which means that supporting improved rail accessibility on the UK rail network is now official ASLEF policy. … Continue reading ASLEF union backs UK rail accessibility!

Lifts at Biggleswade delayed until Summer 2025

Biggleswade station, located on the East Coast Mainline in Bedfordshire, and a growing commuter town, was awarded 'Access for All' funding in April 2019. Since then the project, now on its fifth Network Rail project lead, has faced several delays and we have moved from a completion date of Summer 2022, to a provisional date … Continue reading Lifts at Biggleswade delayed until Summer 2025

An open letter to Network Rail CEO Andrew Haines

In April 2019 Biggleswade station was awarded 'Access for All' funding to provide lifts at the station. Five years on the much delayed scheme has been delayed yet again, and ironically we were informed of this delay in the same week that Andrew Haines set out how Network Rail, the organisation he has been the … Continue reading An open letter to Network Rail CEO Andrew Haines